Development Schedule - 2019.2.26ID Task Namedur Start Finish % Complete1Project358 daysMon 8/19/19Wed 12/30/200%2PROJECT DURATION PHASE 1/ Grading, Retaining Walls, & Planning152 daysMon 8/19/19Tue 3/17/200%3Demolition10 daysMon 8/19/19Fri 8/30/190%4Start Rough Gading10 daysMon 8/19/19Fri 8/30/190%5Rough Grading5 daysMon 8/26/19Fri 8/30/190%15Batter Boards/Control lines13 daysMon 9/2/19Wed 9/18/190%6Onsite Storm and Sewer8 daysMon 9/23/19Wed 10/2/190%16Foundations11 daysMon 9/30/19Mon 10/14/190%9Onsite Fire Main Ph. 1 & 210 daysThu 10/3/19Wed 10/16/190%7Onsite Joint Trench Rule 15/1610 daysMon 10/7/19Fri 10/18/190%17Panel Concrete 24 daysMon 10/21/19Thu 11/21/190%10Site Concrete15 daysMon 11/4/19Fri 11/22/190%11Site Lighting10 daysMon 11/18/19Fri 11/29/190%18Thanksgiving2 daysThu 11/28/19Fri 11/29/190%12Irrigation Sleeves & Mains8 daysFri 11/29/19Tue 12/10/190%21Offsite Sewer and Storm4 daysMon 12/9/19Thu 12/12/190%25Water Service Supplys3 daysMon 12/9/19Wed 12/11/190%26Water Main Ext.7 daysMon 12/16/19Tue 12/24/190%13Rock & Pave Parking Lot5 daysMon 12/23/19Fri 12/27/190%14Christmas2 daysTue 12/24/19Wed 12/25/190%27Offsite Streetwork6 daysMon 1/6/20Mon 1/13/200%22Offsite Lighting5 daysTue 1/14/20Mon 1/20/200%23Grade/Rock City Sidewalk3 daysTue 1/21/20Thu 1/23/200%24City Walk / Curb & Gutter5 daysMon 1/27/20Fri 1/31/200%8PG&E Wire/Transf/Conn.8 daysMon 2/3/20Wed 2/12/200%19Set Swtchgr & Elect Rgh-in15 daysMon 2/17/20Fri 3/6/200%20Punch & Close7 daysMon 3/9/20Tue 3/17/200%28PROJECT DURATION PHASE 2: Building/ Construction203 daysMon 3/23/20Wed 12/30/200%29Building Pads4 daysMon 3/23/20Thu 3/26/200%30Rough Grade Parking Lot5 daysFri 3/27/20Thu 4/2/200%40Certify Pads3 daysThu 4/2/20Mon 4/6/200%41Batter Boards/Control lines7 daysTue 4/7/20Wed 4/15/200%42Plmbg/Elect Underground11 daysThu 4/16/20Thu 4/30/200%43Foundations11 daysThu 4/16/20Thu 4/30/200%44Slab on Grade 10 daysWed 4/29/20Tue 5/12/200%31Onsite Storm 8 daysThu 4/30/20Mon 5/11/200%32Onsite Sewer Connection1 dayTue 5/12/20Tue 5/12/200%35Onsite Fire Main Ph. 28 daysTue 5/12/20Thu 5/21/200%33Onsite Joint Trench Rule 15/1610 daysWed 5/13/20Tue 5/26/200%34PG&E Wire/Transf/Conn.8 daysWed 5/27/20Fri 6/5/200%36Site Concrete15 daysWed 5/27/20Tue 6/16/200%45Panel Concrete 24 daysMon 6/1/20Thu 7/2/200%37Site Lighting10 daysWed 6/17/20Tue 6/30/200%38Irrigation Sleeves & Mains8 daysWed 7/1/20Fri 7/10/200%46Panel Lift 3 daysFri 7/3/20Tue 7/7/200%47Structural Steel 10 daysFri 7/10/20Thu 7/23/200%48Panelized Roof System 16 daysFri 7/24/20Fri 8/14/200%39Rock & Pave Parking Lot5 daysMon 7/27/20Fri 7/31/200%49Built-up Roofing20 daysMon 8/3/20Fri 8/28/200%60Fire Sprinklers8 daysThu 8/27/20Mon 9/7/200%50Electrical Rooms4 daysFri 8/28/20Wed 9/2/200%53Exterior Framing8 daysTue 9/1/20Thu 9/10/200%52Roll-Up Doors5 daysFri 9/11/20Thu 9/17/200%51Set Swtchgr & Elect Rgh-in15 daysMon 9/14/20Fri 10/2/200%54EIFS8 daysFri 9/18/20Tue 9/29/200%55Sheet Metal6 daysWed 9/30/20Wed 10/7/200%56Glass & Glazing10 daysThu 10/8/20Wed 10/21/200%57Metal Canopies6 daysWed 10/21/20Wed 10/28/200%61Painting6 daysThu 10/22/20Thu 10/29/200%62Interiors & Finishes40 daysThu 10/29/20Wed 12/23/200%59Landscaping16 daysTue 11/3/20Tue 11/24/200%58Slate Cladding10 daysMon 11/9/20Fri 11/20/200%63Punch & Close5 daysThu 12/24/20Wed 12/30/200%PROJECT DURATION PHASE 1/ Grading, Retaining Walls, & PlanningPROJECT DURATION PHASE 1/ Grading, Retaining Walls, & PlanningDemolitionStart Rough GadingRough GradingBatter Boards/Control linesOnsite Storm and SewerFoundationsOnsite Fire Main Ph. 1 & 2Onsite Joint Trench Rule 15/16Panel Concrete Site ConcreteSite LightingThanksgivingIrrigation Sleeves & MainsOffsite Sewer and StormWater Service SupplysWater Main Ext.Rock & Pave Parking LotChristmasOffsite StreetworkOffsite LightingGrade/Rock City SidewalkCity Walk / Curb & GutterPG & E PG&E Wire/Transf/Conn.Set Swtchgr & Elect Rgh-inPunch & ClosePROJECT DURATION PHASE 2: Building/ ConstructioPROJECT DURATION PHASE 2: Building/ ConstructioBuilding PadsRough Grade Parking LotCertify PadsBatter Boards/Control linesPlmbg/Elect UndergroundFoundationsSlab on Grade Onsite Storm Onsite Sewer ConnectionOnsite Fire Main Ph. 2Onsite Joint Trench Rule 15/16PG&E Wire/Transf/Conn.Site ConcretePanel Concrete Site LightingIrrigation Sleeves & MainsPanel Lift Structural Steel Panelized Roof System Rock & Pave Parking LotBuilt-up RoofingFire SprinklersElectrical RoomsExterior FramingRoll-Up DoorsSet Swtchgr & Elect Rgh-inEIFSSheet MetalGlass & GlazingMetal CanopiesPaintingInteriors & FinishesLandscapingSlate CladdingPunch & CloseJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunQtr 3, 2019Qtr 4, 2019Qtr 1, 2020Qtr 2, 2020Qtr 3, 2020Qtr 4, 2020Qtr 1, 2021Qtr 2, 2021TaskMilestoneSummaryRolled Up TaskRolled Up MilestoneRolled Up ProgressExternal TasksProject SummarySplitRolled Up SplitExternal MilestoneInactive MilestoneInactive SummaryManual TaskDuration-onlyManual Summary RollupManual SummaryStart-onlyFinish-onlyExternal TasksExternal MilestoneProgressDeadlineS. WINCHESTER RESIDENTIAL DEVELOPMENT2575 & 2585 S WINCHESTER BLVD, CAMPBELL, CA 950084/3/06Date: Tue 1/22/19