CC Ordinance 1777-. -
ORDINANCE NO. 1777
BEING AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF
CAMPBELL, AUTHORIZING EXECUTION OF AN AMENDMENT NO. ONE OF
THE DEVELOPMENT AGREEMENT BETWEEN THE CITY OF CAMPBELL AND
900 EAST HAMILTON, LTD., A CALIFORNIA GENERAL PARTNERSHIP.
The City Council of the City of Campbell does ordain as follows:
SECTION ONE: The Mayor of the City of Campbell is hereby authorized to
execute an amendment to the Development Agreement between the City of Campbell
and 900 East Hamilton, Ltd., a California General Partnership, as described in
Exhibit A, entitled Amendment One to Development Agreement, attached hereto and
incorporated herein by reference.
SECTION TWO: This Ordinance shall become effective thirty (30) days
following its passage and adoption and shall be published once within fifteen
(15) days upon passage and adoption in the San Jose Mercury News, a newspaper
of general circulation in the City of Campbell, County of Santa Clara.
PASSED AND ADOPTED this 5th day ofbecember, 1989, by the following roll
call vote:
AYES: Councilmembers: KOTOWSKI, CONANT, BURR, ASHWORTH
NOES: Councilmembers: NONE
ABSENT: Councilmembers: NONE
ABSTAIN: Councilmembers: WATSON
ATTEST:
APPROVED:
f� j� JOIN J. ASHWORTH, MAYOR
7/4�l V-,f � . %e-C /C
BARBARA OLSASKY, CITY CLERK
By- Louise B. Pena, Deputy City Clerk
EXHIBIT A
AMENDMENT NO. ONE TO DEVELOPMENT AGREEMENT
BY AND BETWEEN THE CITY OF CAMPBELL AND
900 E. HAMILTON, LTD., RELATIVE TO THE
DEVELOPMENT KNOWN AS 900 E. HAMILTON AVENUE
This Amendment No. One is entered into this 5th day of December
1989, by and between 900 E. Hamilton, Ltd., a California general partnership
(the "Developer"), and the City of Campbell, a Municipal Corporation (the
"City"), pursuant to the authority of Sections 65864 through 65869.5 of the
California Government Code.
RECITALS:
A. Developer and City are parties to that certain Development Agreement,
dated June 17, 1986 ("Development Agreement").
B. All of the capitalized terms not otherwise defined in this Amendment
No. One shall have the meanings given in the Development Agreement.
C. The City has adopted Ordinance No. 1737, including the exhibits
referred to in said Ordinance passed and approved by City on February 7,
1989, ("New Ordinance") which has the effect of modifying the Planned
Development Permit previously approved by the City in connection with the
Property and attached as Exhibit "2" to the Development Agreement.
Condition No. 16 to the conditions of The New Ordinance attached as Exhibit
D, thereto, requires that the Development Agreement be revised to reflect
the revised project phasing and revised development schedule.
D. By approval and execution of this Amendment No. One the parties wish
to amend the Development Agreement to reflect the revised Planned
Development Permit and the revised phasing and development schedule.
NOW, THEREFORE, it is agreed by the City and Developer as follows;
1. Exhibit 112" to the Development Agreement is hereby amended by
substituting the New Ordinance adopted by the City on February 7, 1989,
which Ordinance and Conditions of Approval (attached as Exhibit D to such
Ordinance) are attached hereto as Exhibit "2" and incorporated herein by
reference.
2. Exhibit "4" (Revised Development Schedule) to the Development
Agreement is hereby amended in full to conform to the form of Exhibit 4
- 2 -
(Revised Development Schedule) attached hereto and incorporated herein by
reference.
3. Except as expressly amended herein, the Development Agreement is in
full force and affect the City and Developer have performed all covenants
and obligations required to be performed through the date hereof pursuant
to such Development Agreement.
Excuted the day and year first above written.
APPROVED AS TO FORM:
William R. Seligmann
City Attorney
By:
CITY OF CAMPBELL
A California Municipal Corporation
John J. Ashworth, Mayor
900 East Hamilton, Ltd.,
A California General Partnership
By:
EXHIBIT 4
DEVELOPMENT SCHEDULE
Phase I (Office Building #1) - Begin Construction on or before December 31,
1988; complete construction on or before March 1, 1990.
Phase II (Office Building 1/2) - Begin construction on or before December 31,
1989; complete construction on or before March 1, 1991.
Phase III (Hotel) - Begin construction on or before December 31, 1993; complete
construction on or before March 1, 1995.