Pre-Application - 2003
May 27, 2003
Mr, Donald Goudy
373 S. Monroe Street, Suite 303
San Jose, CA 95128
Re:
Preliminary Application
File No.: PRE2003-00026
2135 S. Winchester Blvd.
Dear Mr. Goudy:
Thank you for your submittal of a preliminary application for the construction of a new
dental office building located at 2135 S, Winchester Blvd, The subject property is
presently zoned P-D (Planned Development) and is designated as Central Commercial on
the City's General Plan Land Use Map. The construction of a new commercial building
within the P-D Zoning District requires approval of a Planned Development Pennit and
would go to the Planning Commission and City Council for consideration at a public
hearing,
Projects within the P-D Zoning District are required to be consistent with the underlying
General Plan designation. The Central Commercial designation is intended to provide
shopping, services and entertainment. Buildings should edge the street and include retail
commercial uses on the ground floor with either office or residential uses on the second
floor. The long-term vision of the City for this area along Winchester Boulevard includes
the redevelopment of the underutilized properties with multi-story buildings that provide
retail on the ground floor, similar to the Downtown. Therefore, staff recommends that a
revised project be considered that includes retail on the ground floor with office above.
New commercial buildings should be of a superior quality and design, especially in
highly visible locations such as along Winchester Boulevard. This is hard to achieve
with pre-fabricated buildings due to the limited selection and design options that are
offered. A building that is specifically designed for this site would better achieve the
design objectives and superior site design that will be required for the development of
this site,
The City has a Tree Protection Ordinance that requires that any trees, which are healthy
and can be accommodated on site with a proposed development, be protected and
preserved, It is recommended that you preserve the existing significant trees on site that
will serve to better integrate the new project with the surrounding properties,
70 North First Street. Campbell, California 95008-1436 . TEL 408.866.2140 . FAX 408.866.8381 . TOO 408.866.2790
PRE2003-00026 - 2135 S. Winchester Blvd.
Page 2 of2
Your application was distributed to the Public Works Department, Traffic Engineer,
Building Division, Planning Division and the County Fire Department. In addition to the
Planning Division's comments contained in this letter, please find enclosed comments
from the Building Division, Fire Department and Public Works Department. Please note
that these comments are meant to be preliminary, Conditions of approval from each
department would be developed when a formal application is submitted.
Thank you for the opportunity to review these plans. Please do not hesitate to contact me
at (408) 866-2143 or via email at stephaniew@cityofcampbell.com to schedule a meeting
to discuss these comments and the application process.
Sincerely,
s~~~~ Wi "(-
Planner I
end:
Planned Development Permit Application
Building Division Comments, 5/27/03
Public Works Department Comments, 5/19/03
Fire Department Comments, 5/19/03
cc:
Geoff Bradley, Senior Planner
Charles Little, P.O. Box 511, Ben Lomand, CA 95005
CITY OF CAMPBELL
BUILDING INSPECTION DMSION - COMMENTS TO THE DEVELOPMENT REVIEW COMMITTEE
DRC: May 27,2003
ADDRESS:
2135 S. Winchester Blvd.
Project Application: PRE-2003-00026
RECOMMENDATION:
Note: No building code issue has been reviewed at Development Review Committee; it will be reviewed in the
Building Permit process, Please be aware that building codes are changing constantly; plans submitted for
building permit shall comply with the code in effect at that time. Submit permit application together with
required documents to the Building Inspection Division to obtain a building permit. No construction can be
commenced without an appropriate building permit.
It is recommended that this item be forwarded to the Planning Commission for review, with the following
conditions.
TO THE SATISFACTION OF THE BUILDING DIVISION MANAGER/BUILDING OFFICIAL:
1.
PERMITS REQUIRED: A building permit application shall be required for the proposed (n)
commercial structure. The building permit shall include ElectricallPlumbinglMechanical fees
when such work is part of the permit.
2.
CONSTRUCTION PLANS: The conditions of Approval shall be stated in full on the cover
sheet of construction plans submitted for building permit.
3.
SIZE OF PLANS: The minimum size of construction plans submitted for building permits shall
be 24 in. X 36 in.
4.
PLAN PREPARATION: This project requires plans prepared under the direction and oversight
of a California licensed Engineer or Architect. Plans submitted for building permits shall be
"wet stamped" and signed by the qualifying professional person.
5.
SOILS REPORT: Two copies of a current soils report, prepared to the satisfaction of the
Building Official, containing foundation and retaining wall design recommendations shall be
submitted with the building permit application. This report shall be prepared by a licensed
engineer specializing in soils mechanics.
6.
SITE PLAN: Application for building permit shall include a competent site plan that identifies
property and proposed structures with dimensions and elevations as appropriate. Site plan shall
also include site drainage details. Site address and parcel numbers shall also be clearly called
out. Site parking and path of travel to public sidewalks shall be detailed.
J:\Building ORC Comments\2135swinchesterblvd.doc
7.
8.
9.
FOUNDATION INSPECTIONS: A pad certificate prepared by a licensed civil engineer or land
surveyor shall be submitted to the project building inspector upon foundation inspection. This
certificate shall certify compliance with the recommendations as specified in the soils report and
the building pad elevation and on-site retaining wall locations and elevations are prepared
according to approved plans. Horizontal and vertical controls shall be set and certified by a
licensed surveyor or registered civil engineer for the following items:
a.
b.
c.
pad elevation
finish floor elevation (first floor)
foundation comer locations
TITLE 24 ENERGY COMPLIANCE: California Title 24 Energy Standards Compliance forms
shall be blue-lined on the construction plans. Compliance with the Standards shall be
demonstrated for conditioning of the building envelope and lighting of the building.
SPECIAL INSPECTIONS: When a special inspection is required by U.B.C. Section 1701, the
architect or engineer of record shall prepare an inspection program that shall be submitted to the
Building Official for approval prior to issuance of the building permits, in accordance with
U.B.C Section 106.3.5. Please obtain City of Campbell, Special Inspection forms from the
Building Inspection Division Counter.
10.
The City of Campbell, standard Santa Clara Valley Non-point Source Pollution Control Program
specification sheet shall be part of plan submittal. The specification sheet (size 24" X 36") is
available at the Building Division service counter.
11.
TITLE 24 ACCESSIBILITY - COMMERCIAL: On site general path of travel shall comply
with the latest California Title 24 Accessibility Standards. Work shall include but not be limited
to accessibility to building entrances from parking facilities and sidewalks.
12.
TITLE 24 ACCESSIBILITY - COMMERCIAL: Projects seeking to use the Title 24 Hardship
exemption clause shall blue-line completed, City of Campbell "20%" exemption form on
submitted construction plans. Form is available at Building Division service counter.
13.
APPROV ALS REQUIRED: The project requires the following agency approval prior to
issuance of the building permit:
a. West Valley Sanitation District
b. Santa Clara County Fire Department
c. School District:
i) Campbell Union School District (378-3405)
ii) Campbell Union High School District (371-0960)
iii) Moreland School District (874-2900)
iv) Cambrian School District (377-2103)
Bay Area Air Quality Management District (Demolitions Only)
Santa Clara County Department of Environmental Health
d.
e.
J:\Building ORC Comments\2135swinchesterblvd.doc
14.
P.G.& E.: Applicant is advised to contact Pacific Gas and Electric Company as early as
possible in the approval process. Service installations, changes and/or relocations may require
substantial scheduling time and can cause significant delays in the approval process. Applicant
should also consult with P.G. and E. concerning utility easements, distribution pole locations and
required conductor clearances.
J:\Building ORC Comments\2135swinchesterblvd.doc
MEMORANDUM
CITY OF CAMPBELL
TO:
Melinda Denis, Project Planner
FROM: 4Lynn Penoyer, Land Development Manager
Ed Arango, Associate Engine~
SUBJECT: DRC APPLICATION
DATE: 05/19/03
Site Address: 2135 S. Winchester Boulevard
For File No(s): PRE 2003-026
Project Description: New dental/office building
Applicant: Donald Goudy
PUBLIC WORKS DEPARTMENT PRELIMINARY CONDITIONS OF APPROVAL
1.
Preliminary Title Report: Prior to issuance of any grading or building permits for the site,
the applicant shall provide a current Preliminary Title Report.
2,
Street Improvements: Prior to issuance of any grading or building permits for the site, the
applicant shall execute a street improvement agreement, cause plans for public street
improvements to be prepared by a registered civil engineer, pay various fees and deposits,
post security and provide insurance necessary to obtain an encroachment permit for
construction of the standard public street improvements, as required by the City Engineer.
The fee for a non-utility encroachment permit application is currently $260,00. The plans
shall include the following:
a. Remove damaged curb, gutter, and sidewalk;
b. Remove driveways to accommodate new driveway locations;
c, Installation of new curb, gutter and sidewalk;
d. Installation of new ADA compliant driveways;
e, Installation of tree wells, street trees and irrigation;
f. Construction of conforms to existing public and private improvements, as
necessary.
3.
Water Meter(s) and Sewer Cleanout(s): Existing and proposed water meter(s) and sewer
cleanout(s) shall be installed on private property behind the public right-of-way line.
4.
Utilities: All new on-site utilities shall be installed underground per Section 20.36.150 of
the Campbell Municipal Code for any new or remodeled buildings or additions. Applicant
shall comply with all plan submittals, permitting, and fee requirements of the serving utility
companIes.
l:\LandDev\Conditions\Winchester 2135 Pre.DOC
Page 1 of 2
2135 S. Winchester Blvd.
5,
Utility Coordination Plan: Prior to issuance of building permits for the site, the applicant
shall submit a utility coordination plan and schedule for approval by the City Engineer for
installation and/or abandonment of all utilities. Streets that have been resurfaced within the
previous five years will require boring and jacking for all new utility installations.
Applicant shall also prepare pavement restoration plans for approval by the City Engineer
prior to any utility installation or abandonment.
6,
Grading and Drainage Plan: Prior to issuance of any grading or building permits for the
site, the applicant shall conduct hydrology studies based on a ten-year storm frequency,
prepare an engineered grading and drainage plan, and pay fees required to obtain necessary
grading permits. The plans shall comply with the 1998 edition of the California Building
Code including Chapters 10, 11, 18,33, and Appendix Chapter 33,
7.
Storm Drain Area Fee: Prior to issuance of any grading or building permits for the site, the
applicant shall pay the required Storm Drain Area fee of $2,500,00 per net acre, which is
$575,00,
8,
Storm Water Pollution Prevention Measures: Prior to issuance of any grading or building
permits, the applicant shall comply with the National Pollution Discharge Elimination
System (NPDES) permitting requirements, the California Storm Water Best Management
Practices Handbook prepared by the Storm Water Quality Task Force, Santa Clara Valley
Water District requirements, and the City of Campbell Municipal Code regarding storm
water pollution prevention.
The City will provide the applicant with information to assist in complying with this
condition of approvaL The primary objective is to improve the quality and reduce the
quantity of storm water runoff to the Bay,
J:\LandDev\Conditions\Winchester 2135 Pre.DOC
Page 2 of 2
FIRe. DEPARTMENT
SANTA CLARA COUNTY
PLr". REVIEW NUMBER 03 1006
BLDG PERMIT NUMBER
14700 Winchester Blvd.. Los Gatos, CA 95032-1818
(408) 378-4010 . (408) 378-9342 (fax) . www.sccfd.org
CONTROL NUMBER
-
FILE NUMBER PLN 2003-26
DEVELOPMENT REVIEW COMMENTS
CODE/SEC. I
SHEET 11 REQUIREMENT
Pre-application review of a proposed Planned Development Permit for a new 2,943
square foot dental! office building.
UFC
Appendix
III-A
1 Review of this Developmental proposal is limited to acceptability of site access and
water supply as they pertain to fire department operations, and shall not be
construed as a substitute for formal plan review to determine compliance with
adopted model codes. Prior to performing any work the applicant shall make
application to, and receive from, the Building Department all applicable
construction permits.
2 Required Fire Flow: The fire flow for this project is 1,500 gpm at 20 psi residual
pressure. The required fire flow is available from area water mains and fire
hydrant{s) which are spaced at the required spacing.
UFC
901.4.4
3 Premises Identification: Approved numbers or addresses shall be placed on all
new and existing buildings in such a position as to be plainly visible and legible
from the street or road fronting the property. Numbers shall contrast with their
background.
4 To prevent plan review and inspection delays, the above noted Developmental
Review Conditions shall be restated as "notes" on all pending and future plan
submittals and any referenced diagrams to be reproduced onto the future plan
submittal.
City PLANS SPECS NEW RMDL AS
OCCUPANCY CONST.TYPE
ApplicantName
DATE
PAGE
CBL
0
0
0 0 0
BRITI ROWE
5/19/2003 ~ OF 1
BY
SECJFLOOR
AREA
LOAD
DESCRIPTION
NAME OF PROJECT
Commercial Development
I ~olc~ION Winchester BI
Organized as the Santa Clara County Central Fire Protection District
Serving Santa Clara County and the communities of Campbell, Cupertino, Los Altos,
Los Altos Hills, Los Gotos, Monte Sereno, Morgan Hill, and Saratoga
Hokanson, Wayne
III
~
c,
"
oS' ~c,
4t/lEO
Esthetic and Reconstructive
Dentistry
cd!
LIZ 1-8(0 (
373 S. I1GorGe St. Suite ]03
San Jose. CA, 95128
TeI.408.241.5055
lax. 408.241.5060
www.lllile-dullu,com
May 5, 2003
Pre-application Review
APN: 305-33-019
Address: 2135 S. Winchester Blvd.
Campbell, CA 95008
Zoning C3
The proposed use for this lot is to build a 2943 sq. ft. General Dental Office on the 9583
sq. ft. lot. There is no existing structure on the lot. The office currently has 5 employees
plus the owner operator, a single dentist office. The hours of operation will be 8am to
5pm Monday, Tuesday and Thursday and lOam to 7pm on Wednesday.
The building will be stucco and frame construction with permanent cement foundation.
The framing, electrical, plumbing and interior finish work will be completed off-site and
pre-fabricated units will be shipped and placed on the foundation. Stucco and roofline
decoration will be done on site after delivery.
The design of the exterior can be anything the City of Campbell deems appropriate. I
would like to get their input before final drawings are made. I would also like to make
sure pre-fabricated framing is approved by the City (specifications attached).
I would like to have a setback of 5' on the Winchester and Rincon sides of the property
with 12 parking spaces on the side and rear of the building. This necessitates removal of
some shrubbery, rocks and trees located at the front of the property. I will not be able to
develop the lot if I am not allowed to remove these trees (pictures attached). There will
be new landscaping and trees throughout the rest of the lot. Seven trees will be planted in
front of all diagonal parking spots which is not shown on the site plan. The 5' setback
will be landscaped as well.
The proposed site is presently in escrow. I have 30 days to decide if the proposed
building will be approved or denied. Basically I just need to know if a pre-fabricated
building is OK as long as it is on a permanent foundation and has exterior stucco
decoration and facade per the City's request. I also need to know if the existing
shrubbery and trees at the front of the property can be removed. I cannot commit to
purchasing the lot without this approval.
Thanks for your consideration.
Sincerely,
~~
Don Goudy DDS
RECEIVED
MAY 0 8 2003
CITY OF CAMPBELL
PLANNING DEPT.