CC Resolution 11657RESOLUTION NO. 1165
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CAMPBELL
APPROVING PLANS AND SPECIFICATIONS, AUTHORIZING SOLICITATION
OF BIDS, AUTHORIZING THE CITY ENGINEER TO AWARD A CONSTRUCTION
CONTRACT AND EXECUTE CONTRACT CHANGE ORDERS,
FOR HAMILTON AVENUE MEDIAN AND ROADWAY REHABILITATION PROJECT
14-NN, AND APPROVING BUDGET ADJUSTMENT
WHEREAS, the final plans and specifications have been prepared for the project; and
WHEREAS, the attached budget adjustment has been prepared to provide additional
project funding as a result of additional funding to the City from utility company
reimbursements.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Campbell
hereby approves the plans, specifications and engineer's estimate for the Hamilton
Avenue Median and Roadway Rehabilitation Project 14-NN, authorizes the City
Engineer to issue such plans and specifications for public bid, authorizes the City
Engineer to determine the lowest reasonable and responsible bidder and award a
construction contract in an amount not to exceed $588,546, authorizes the City
Engineer to encumber a construction contingency in an amount not to exceed $58,854
for a total construction contract amount not to exceed $647,400, authorizes the City
Engineer to execute contract change orders within and up to the construction
contingency amount, and approves the attached budget adjustment.
PASSED AND ADOPTED this 15t day of April, 2014 by the following roll call vote:
AYES: COUNCILMEMBERS: Raker, Low, Kotowski, Gristna, Waterman
NOES: COUNCILMEMBERS: None
ABSENT: COUNCILMEMBERS: None
APPROVED:
~ ~1/'~
Richard M. Waterman, Mayor
ATTEST: (~ \\''
cp l'.~t'h
~ Anne bee, City Clerk