PC Res 2236RESOLUTION N0. 2236
BEING A RESOLUTION OF THE PLANNING COMMISSION OF THE
CITY OF CAMPBELL RECOMMENDING APPROVAL OF PLANS, ELE-
VATIONS, AND DEVELOPMENT SCHEDULE TO ALLOW THE CON-
STRUCTION OF AN OFFICE BUILDING ON PROPERTY KNOWN AS
910 CAMPISI WAY (APPLICATION OF SOUTHBAY CONSTRUCTION
DEVELOPMENT C0.) PD 83-06
Plans, elevations, and development schedule for the construction of an
office building to be located on property known as 910 Campisi Way in a
PD (Planned Development/Commercial) Zoning District have been presented
for approval by Southbay Construction and Development Company.
After notification and public hearing as specified by law on said pro-
posed amencbnents, as filed in the Office of the Planning Department on
PD 83-06, and after presentation by the Planning Director, proponents
and opponents, the hearing was closed.
After due consideration of all evidence presented, the Planning Commission
did find as follows:
That the establishment, maintenance, and operation of the
proposed use will not be detrimental to the health, safety,
peace, morals, comfort or general welfare of the persons
residing or working in the neighborhood of such use, or
detrimental or injurious to property and improvements in
the neighborhood or the general welfare of the City.
Based on the above findings, the Planning Commission did recommend approval
of plans, elevations, and development schedule as presented and further re-
commends that the City Council enact the Ordinance attached hereto as Exhibit
"A" adopting said plans, elevations, development schedule, and conditions of
approval for that portion of the above-mentioned Planned Development Zone.
PASSED AND ADOPTED this 8th day of November 1983 by the following roll call
vote:
AYES: Commissioners: Kasolas,
Dickson,
NOES: Commissioners: None
ABSENT: Commissioners: None
ATTEST: Arthur A. Kee
Secretary
Campos, Meyer, Fairbanks, Howard,
Kotowski
APPROVED: r2ichael F. Kotowski
airman
ORDINANCE N0.
BEING AN ORDINANCE OF TTTE CITY COUNCIL OF THE CITY OF
CAMPBELL ADOPTING PLANS, ELEVATIONS, DEVELOPMENT SCHEDULE,
AND CONDITIONS OF APPROVAL 1~R THE PLANNED DEVELOPA~VT
ZONE ESTABLISHED BY ORDINANCEOF THE CITY OF CAMPBELL
(APPLICATION OF SOUTHBAY CONSTRUCTION AND DEVELOPMENT
COT4PANY, MR WILLIAM JURY, PD 83-06).
The City Council of the City of Campbell does ordain as follows:
SECTION ONE: That the Zoni:
changed and amended by adopting
and Elevations; Exhibit B entity
entitled Map of Said Property; a
Approval, as per the application
Company on property Imown as 910
Zoning District. Copies of said
the Planning Department.
g Map of the City of Campbell is hereby
he attached Exhibit A entitled Plans
d Development Schedule; Exhibit C
d Exhibit D entitled Conditions of
of Southbay Construction ald Development
Campisi Way in a Planned Development
Exhibits are on file in the Office of
SECTION TWO: This ordinance shall become effective 30 days follow-
ing its passage and adoption and shall be published once within 15 days
upon passage and adoption in the Campbell Press, a newspaper of general
circulation in the City of Campbell, County of Santa Clara.
PASSED AND ADOPTED this day of
following roll call vote:
AYES: Councilmen:
NOES: Councilmen:
ABSENT: Councilmen:
APPROVED:
198 by the
DEAN R. E IN, MAYOR
ATTEST:
G. OOYNE, CITY CLERK
EXHIBIT B
STANDARD DEVELOPMENT SCHEDULE
FILE N0: PD 83-06 '
APPLICANT: JURY, W. - SOUT(-iBAY CONSTRUCTION 00.
SITE ADDRESS: 910 CAMPISI WAY
1. Construction to begin within six months of final approval.
2. Construction to be completed within one year of starting
date.
NOTE: Above development schedule is a standard used by the
Planning Department when applicant has not submitted a schedule
for his project.
EXHIBIT D
COND 1 T IONS OF APPROVAL : PD 83-06
APPL 1 CAT 1 ON of : JURY, W. - SOUIHBAY OJNSTRUCTION
Page 1 P. C. MTG.: 11/8/83 ;--~
n a Revised elevations and/or site plan to be approved by~the Plate nn_~in~c
Director upon recommendation of the Architectural Advisor, within
30 days of the Planning Commission approval.
A Revised elevations ands site plan to be approved by the Site &
Architectural Review Committee with-
in 30 days of Planning Commission approval.
B Property to be fenced and landscaped as indicated and/or added in
red on plans. Landscaping and fencing shall be maintained in
accordance with the approved plans.
C Landscaping plan indicating type and size of plant material, and
location of irrigation system to be submitted for approval of the
Site & Architectural Review Committee and/or Planning Commission
prior to application for a building permit.
n a Landscaping plan indicating type and size of plant material, and
location of irrigation system to be submitted for approval of the
Planning Director prior to application fora building permit.
D Fencing plan indicating location and design details of fencing to
be submitted for approval of the Planning Director prior to applica- --~
tion for building permit. '
E Applicant to either (1) post a faithful performance bond in the
amount of $ 10 000 to insure landscaping, fencing, and striping
of parking areas wit in 3 months of completion of construction; or
(2) file written agreement to complete landscaping, fencing and strip-
ing of parking areas prior to application for a building permit.
F Applicant to submit a plan, prior to installation of PG&E utility
(transformer) boxes, indicating the location of the boxes and
screening(if boxes are aboveground) for approval of the Planning
Director.
n a Applicant to submit a letter, satisfactory to the City Attorney,
limiting the use of the property to: square feet of
office use, square feet of speculative industrial
use, and square feet of warehouse use, prior to
issuance of a bui ing permit.
G All mechanical equipment on roofs and all utility meters to be
screened as approved by the Planning Director.
H- Building occupancy will not be allowed until public improvements
are installed.
*n/a: not applicable to this application.
CONDITIONS OF APPROVAL: PD 83-06
APPLICATION OF: SOUII-IBAY CONSTRUCTION
Page 2
The applicant is notified as part of this application that helshe is required
to meet the following, conditions in accordance with Ordinance of the City of
Campbell and Laws of the State of California.
I All parking and driveway areas to be developed in compliance with
Section 21.50 of the Campbell Municipal Code. All parking spaces
to be provided with appropriate concrete curbs or bumper guards.
J Underground utilities to be provided as required by Section
20.16.070 of the Campbell Punicipal Code.
K
Plans submitted to the Building Department for plan check shall
indicate clearly the location of all connections for underground
utilities including water, sewer, electric, telephone and tele-
vision cables, etc.
L Sign application to be submitted in accordance with provisions of
the Sign Ordinance for all signs, No sign to be installed until
application is approved and permit issued by the Building Depart-
ment (Section 21.68.030 of the Campbell Municipal Code).
M Ordinance No. 782 of the Campbell Municipal Code stipulates that
any contract for the collection and disposal of refuse, garbage,
wet garbage and rubbish produced within the limits of the City of
Campbell shall be made with Green Valley Disposal Company. This
requirement applies to all single-family dwellings, multiple apart-
ment units, to all commercial, business, industrial, manufacturing,
and construction establishments.
N Trash container(s) of a size and quantity necessary to serve the
development shall be located in area(s) approved by the Fire De-
partment. Unless otherwise noted, enclosure(s) shall consist of
a concrete floor surrounded by a solid wall or fence and have
self-closing doors of a size specified by the Fire Department.
All enclosures to be constructed at grade level,
0 Applicant shall comply with all appropriate State and City re-
quirements for the handicapped.
~/a Noise levels for the interior of residential units shall comply
with minimum State (Title 25) and local standards as indicated
in the Noise Element of the Campbell General Plan.
n(a Applicant is hereby notified that he will be required to pay
Park Dedication In-Lieu Fee which will be assessed at the time
the subdivision map is submitted.
STANDARD FIRE HAZARD ABATEMENT COMMENT: The applicant is hereby notified that
the property is to be maintained free of any combustible trash, debris and weeds,
until the time that actual construction ctimmences. A11 existing structures shall
be kept secured by having windows boarded up and doors sealed shut, or be demolish-
ed or removed from the property. Sect. 11.201 & 11.414, 1979 Ed. Uniform Fire Code.
CONDITIONS OF APPROVAL: pD 83-06
APPLICATION OF: SOUTHBAY OONSTRUCTION
Page 3
PUBLIC WORKS DEPARTNID~IT
P. Submit a traffic impact analysis concentrated on the intersections
of Bascom Ave. with Campisi Way and Hamilton Ave.
Q. Obtain an excavation permit for all work within the street right-of-way.
BUILDING DEPARTNIDVT
R. Roof covering shall be fire retardant.
FIRE DEPAR'IT~NT
S. Provide an automatic fire extinguisher system. Required Fire Flow =
1226 G.P.b1.
T. Provide 2A-lOBC fire extinguishers.
U. Sprinkler system to be monitored by a licensed central station.
V. The sprinkler F.D.C. to be located adjacent to the existing fire
hydrant, in front of the development.
The applicant is notified that he/she shall comply with all applicable Codes or
Ordinances of the City of Campbell which pertain to this development and are not
herein specified.